In June 2017, Sieyuan was awarded a series compensation equipment project in Turkey. The project includes 6 series compensation platforms. It is the first SC project in Turkey. Sieyuan Electric is responsible for design, procurement, and supervision of installation, test and commissioning.
Sieyuan has delivered all the equipments to site. The installation work was going successfully under our supervision. The main equipment MOV, capacitor bank, damping resistor, damping reactor, GAP and secondary equipment has been well installed and tested. The equipments are now waiting for the request of commissioning.
After completion of the project, the SC equipment will greatly improve efficiency of the power transmission, and will meet the increasing demand of electricity.