Belgium 220kV Reactor Successfully Passed FAT

2024-03-25

On  February 27th, 2024, the Belgian project's 220kV shunt reactor--designed, manufactured and supplied by Sieyuan Toshiba Transformer Co., Ltd.--has passed the acceptance test with the witness of both supervisory engineers from TUV and EDF (China), appointed respectively by the contractor and the project owner.

During the FAT process, the two engineers made careful inspections on the exterior of the product and supervised all the performance tests, which later turned out to had passed at the first try. The FAT also passed the third-party type test conducted by ASTA, which further proved that the product's performance and indexes are in full accordance with the IEC international standards.