Ghana Bolgatanga 330 kV Substation EPC: Ghana-Burkina Faso Grid Interconnection Hub

Aerial view of the Bolgatanga 330 kV substation in Ghana's Upper East Region

Located in Ghana's Upper East Region, the Bolgatanga Substation serves as an interconnection point between Ghana's 330 kV transmission network and the 225 kV cross-border transmission line towards Burkina Faso. Sieyuan delivered a full-scope EPC solution covering engineering, equipment supply, civil works, installation, testing, and commissioning. The project features breaker-and-a-half configurations for dual voltage levels and involved complex management of multiple technical interfaces.

EPC
Get in Touch

Project Overview

Sieyuan Electric delivered the full-scope EPC of the Bolgatanga Substation in Ghana's Upper East Region, connecting Ghana's 330 kV transmission network with the 225 kV cross-border line towards Burkina Faso.

Aerial view of the Bolgatanga substation switchyard with surrounding savanna landscape
Bolgatanga substation gantries, power transformer and switchyard lit at dusk
High-voltage switchyard equipment and steel gantries illuminated at night in Bolgatanga

Project Background

The Bolgatanga Substation Project was developed to strengthen transmission infrastructure in northern Ghana and improve the reliability of power supply in the region. As a key transmission node, the substation integrates Ghana's 330 kV backbone network with the 225 kV cross-border transmission system toward Burkina Faso.

The project required an integrated EPC solution covering substation engineering, major equipment supply, civil works, installation, testing, commissioning, and coordination with owner-supplied main transformers.

Key Challenges

  • Multi-voltage system integration

    The substation incorporates both 330 kV and 225 kV systems, requiring coordinated design of insulation levels, equipment ratings, electrical clearances, and system interfaces to ensure safe and reliable operation.

  • Cross-border grid interface coordination

    The connection between Ghana's transmission network and the Burkina Faso transmission line required coordination of protection settings, communication protocols, control interfaces, and operational requirements among multiple stakeholders.

  • Complex protection and control commissioning

    Both the 330 kV and 225 kV systems adopt breaker-and-a-half configurations, involving complex protection logic such as breaker-failure protection, auto-reclosing, synchronism-check, and interlocking functions. Integrated commissioning of primary and secondary systems was essential for reliable energization.

  • Multi-interface EPC execution

    The project required close coordination with owner-supplied main transformers, including equipment parameters, physical interfaces, installation schedules, and commissioning arrangements. Site execution also required careful planning for transportation, installation, and high-voltage testing.

Sieyuan Solution

  • Integrated high-voltage system engineering

    Sieyuan performed integrated engineering for the 330 kV and 225 kV sections, covering electrical design, insulation coordination, equipment selection, and interface management. The solution ensured coordinated operation between different voltage levels.

  • Integrated protection, automation, and communication design

    Sieyuan developed coordinated protection, control, automation, and communication solutions for the breaker-and-a-half configurations. Integrated design of protection logic and system interfaces reduced commissioning risks and improved overall system coordination.

  • In-house equipment supply and system integration

    Sieyuan supplied major primary and secondary equipment, including dead-tank circuit breakers, disconnectors, instrument transformers, surge arresters, protection and control systems, substation automation systems, and communication equipment. Integrated equipment supply improved technical consistency and simplified interface coordination.

  • Full-scope EPC execution and interface management

    Sieyuan managed engineering, procurement, civil works, installation, testing, and commissioning under an integrated EPC framework. Coordination with owner-supplied main transformers was carried out throughout project execution to support smooth system integration and commissioning.

Technical Highlights

  • Integrated primary and secondary equipment supply
    Included circuit breakers, disconnectors, instrument transformers, surge arresters, protection systems, automation systems, and communication equipment.

  • Owner-supplied transformer interface management
    Coordinated equipment parameters, physical interfaces, installation schedules, and commissioning requirements for owner-supplied main transformers.

  • Cross-border grid interface coordination
    Coordinated protection, communication, control, and operational requirements between the connected transmission systems.