Sieyuan Electric undertook the EPC works for two 132/33 kV AIS substations at Kuje and Wumba and a 6 km, 132 kV underground cable for TCN's Abuja Transmission Ring Scheme.
Abuja Transmission Ring Scheme Lot 5: EPC of 132 kV Substations and Underground Cable

As part of the Abuja Transmission Ring Scheme developed by the Transmission Company of Nigeria (TCN) with financing support from the French Development Agency (AFD), LOT 5 comprises two 132/33 kV air-insulated switchgear (AIS) substations at Kuje and Wumba, together with an associated 6 km, 132 kV underground cable line. Sieyuan Electric undertook the EPC works and supplied major primary and secondary equipment to reinforce transmission infrastructure in southern Abuja and support improved electricity supply to surrounding communities.
Project Overview
Project Background
Nigeria’s capital region has faced longstanding transmission constraints and electricity supply shortages. The Abuja Transmission Ring Scheme aims to strengthen the regional grid, with LOT 5 providing key substation infrastructure to support power delivery to Kuje, Dafara, Wumba-Lokogoma and nearby areas. The project combines challenging hillside construction conditions with stringent engineering review requirements and complex high-voltage protection and control schemes.
Key Challenges
Complex hillside terrain
Significant elevation differences at both sites required extensive excavation and backfilling, together with slope protection, retaining structures and drainage systems to ensure long-term site stability.
Stringent engineering review
Detailed reviews of site layouts, platform elevations, foundations, gantry structures and drainage required repeated design optimization to balance terrain constraints, structural stability and construction feasibility.
Complex 132 kV protection and control
The breaker-and-a-half configuration at both substations required coordinated protection, interlocking, breaker-failure protection and auto-reclosing logic. Comprehensive verification was essential to ensure correct interaction between primary equipment and secondary systems.
Sieyuan Solution
Integrated hillside civil engineering
Sieyuan coordinated site grading, earthwork balance, slope stabilization, foundations and drainage to address the elevation differences at both sites. This integrated approach supported site stability and equipment installation while accounting for construction constraints.
Coordinated civil and electrical design
Civil and electrical interfaces were reviewed together throughout the engineering process. Site layouts, equipment foundations, gantry structures and cable routes were optimized in response to client and consultant reviews, helping improve constructability and reduce potential interface conflicts.
Integrated protection and control engineering
Sieyuan coordinated protection, control, interlocking, breaker-failure protection and auto-reclosing logic for the 132 kV breaker-and-a-half schemes. Progressive verification at string, bay and system levels supported the coordinated operation of primary equipment and secondary systems during commissioning.
Integrated equipment supply and EPC coordination
Sieyuan supplied major equipment, including power and earthing transformers, circuit breakers, disconnectors, instrument transformers, surge arresters, protection and control systems, and AC/DC systems. Engineering, procurement, equipment supply and site activities were coordinated across Kuje and Wumba to manage technical interfaces and support parallel implementation.
Technical Highlights
Two 132/33 kV AIS substations
Kuje: 3 × 60 MVA; Wumba: 2 × 60 MVA.132 kV breaker-and-a-half configuration
Coordinated protection and control engineering for complex high-voltage switching schemes.6 km underground cable connection
Associated 132 kV infrastructure linking the project into the wider transmission network.Integrated EPC delivery
Primary and secondary equipment supply combined with hillside civil engineering and multi-site project coordination.